Laval
The City of Laval requires a permit before enlarging a single-family house. Its examples: adding a second storey, a garage built into the house, a permanent carport attached to the house, and a solarium or veranda attached to the house.
Fee: $92 for the first $20,000 of work, plus $2.50 per additional $1,000. An $80,000 addition comes to about $242. Water and sewer connections, if needed, are billed separately (the city lists $450 for the first dwelling for a connection permit).
Delay: about 50 days, counted only once every required document has been received, and longer if the property is under a PIIA or needs a minor variance.
Steps: check whether a PIIA applies, prepare the file, submit it, pay, the city analyses it, the permit arrives by email, then an inspector visits. The Service de l'urbanisme, 1333, boulevard Chomedey, Laval offers appointments in person or by video before you apply.
Montreal boroughs (including Pierrefonds-Roxboro and L'Île-Bizard)
The City of Montreal requires the permit before any work starts. Typical documents include the certificate of location, a site plan showing the existing building and the addition, elevations, sections and floor plans, material details, a building sheet and a cost estimate including taxes. Several boroughs require plans prepared by an architect and structural, mechanical and electrical plans sealed by an engineer.
Fee: the analysis fee is $9.80 per $1,000 of estimated work cost, with a minimum in some boroughs; for an $80,000 addition that is about $784.
In Pierrefonds-Roxboro, construction projects including additions must go through a PIIA under bylaw CA29 0042. The urban planning division checks the file, the Comité consultatif d'urbanisme makes a recommendation and, in some cases, the borough council approves it before the permit is processed. The borough recommends booking an appointment with its permit office first.
Independent West Island cities
Kirkland, Dollard-des-Ormeaux, Beaconsfield, Pointe-Claire, Dorval, Baie-D'Urfé and Sainte-Anne-de-Bellevue are separate municipalities, each with its own permit office, fees and zoning. Their rules for setbacks, height and materials differ, so the first step is always to confirm them for the exact address.
Plan the calendar
Between design, plans and the permit delay, an addition often needs a few months before construction can begin. Homeowners who start the design in fall or winter are usually the ones building in spring.
Sources
City of Laval, single-family addition permit page; City of Montreal, permit for the enlargement of a building; City of Montreal, renovations, additions and new construction in Pierrefonds-Roxboro. Rules change: always confirm with your city before filing.
Official sources
- City of Laval: addition permit
- City of Montreal: addition permit
- Pierrefonds-Roxboro: additions and PIIA
Planning this project?
Tell us about it in 60 seconds or call 514-241-4530. We visit, measure and send a fixed price with a dated schedule. The visit is free in the West Island; elsewhere a visit fee applies based on your location.